Commercial Construction Project Dispute

We represented an interior finishes subcontractor in a dispute among the owner, general contractor and key subcontractors on a large commercial project. The subcontractor's claim in excess of $1.5 million dollars (on a contract of $1.3 million dollars) arose from extra work, differing site conditions, out of sequence work and acceleration. The claim was settled through negotiation for seven figures on the eve of arbitration.